Our new house is under a very tight schedule. WE NEED YOU TODAY!
Jan 28 & 29 – complete repainting – ceilings, walls. Saturday the volunteer crew did great. Today we have to complete the remaining 60%. PLEASE HELP US! 5 Village Ln., Westbrook , ME 9:30 am – 4 pm
Monday, Jan 30 – bathroom tile – contractor.
Tues, Jan 31 – we can do nothing because I have appointments at Lahey Clinic in Boston.
Wed – Thursday, Feb 1-2- hardwood flooring. Contractor.
Fri., Feb, 3 – set aside incase needed by contractor. Propane inspection to route line for range
Sat, Feb 4 – Robin working on odds and ends.
Mon., Feb 6 – have propane line run
Tues., Feb. 7 – appliances delivered and installed
Fri., Feb 10 POD delivered
Sat., Feb. 11 – ALL HANDS ON DECK as all that is in the POD is brought in the house.
Mon., Feb 13 – cable and Internet installed.
Tight, huh? That’s why we need your help today finishing the painting. We’d rather not be painting and dripping when our new floor is in.
PLEASE COME HELP ROBIN TODAY. Give what time you have. If you have a roller and pole, please bring it.
Robin will be there from 9:30 am – 4:00 pm. Call her at 239-4289 to tell her you are coming.
5 Village Lane, Westbrook, 04092.